Project Scope:
Single story home on crawl space foundation had experienced fairly severe settlement. As a result of settlement, lateral loads were causing walls to buckle outward.
Date: June, 2004
Structure: Family Residence, Benton AR
Contractor: Powerlift Systems
Engineer: Akii Engineering
Material Used: Fortress Carbon Fiber 4" grid straps in Fortress Epoxy matrix.
Project Scope:
Single story home on crawl space foundation had experienced fairly severe settlement. As a result of settlement, lateral loads were causing walls to buckle outward.
![]() |
![]() |
Solution:
After piers were installed and foundation lifted to near original level, Fortress Carbon Fiber was used to tie foundation back together.
![]() |
![]() |
Observations:
Fortress Carbon Kevlar Grid was installed in one day, allowing foundation to be re-parged coated for aesthetics the next day.